Radical planning reform needed to tackle energy constraints, Cambridge professor says

With Scotland’s electricity grid struggling to keep pace with the growth of renewable energy, a leading energy expert says radical planning reform is needed to cut costs and tackle growing constraints.

The high cost and slow speed of rebuilding the UK’s energy network to link wind farms with centres of population could make many projects uneconomic, according to a leading electricity markets expert.

That is the view of Emeritus Professor David Newbery, a specialist in the regulation of electricity markets.

With the cost of transmission constraints now at £1.7 billion a year nationally, and £9.1 million for Shetland’s Viking wind farm in 2026 so far, these costs have become a growing issue.

Speaking to Shetland News earlier this week, Professor Newbery expressed some sympathy for communities in Shetland and elsewhere in Scotland calling for a moratorium on new developments until a proper energy transition plan is in place.

He also agreed with local concerns that any new wind farm built in Shetland may primarily serve to collect constraint payments rather than provide reliable energy due to the islands’ current export limitations.

“If you add an extra wind farm, all it does is push other people off the system, and they get paid,” he said.

To overcome the current bottleneck, the director of the Energy Policy Research Unit (EPRU) at the University of Cambridge advocated for an urgent and radical overhaul of the planning system to make building transmission capacity easier.

He said current policies by energy regulator Ofgem and the National Energy System Operator (NESO) to favour offshore transmission lines, partly to avoid conflict with residents, were the wrong approach, as these were five to 10 times more expensive than building infrastructure on land.

That, he said, would add a further £100 to consumers’ annual electricity bills and make wind more expensive than electricity from gas.

Instead, in order to “not obstruct progress”, he proposed:

  • building additional pylons alongside existing ones to minimise visual impact and bypass lengthy planning processes;
  • implementing high-voltage direct current (HVDC) lines for long-distance bulk power movement;
  • adopting “pre-consented corridors or regions”, similar to those in other European countries, to avoid individual consent processes for every project;
  • making regulatory changes so developers cannot connect until sufficient transmission capacity exists.

He described the Scottish grid as “weak”, with large parts using just 132 kilovolts instead of the 440 kilovolts found in the main interconnected systems in England.

Professor Newbery added that upgrading infrastructure originally designed for centralised coal and coastal nuclear power stations was very slow, pointing to the 22-year process to upgrade the Denny to Beauly transmission line.

The “B6 constraints” at the border between Scotland and England also cause significant congestion when wind speeds are high across both countries, he added.

The Viking Energy wind farm has been operational since summer 2024. Photo: Shetland News

“Due to these constraints, some newer Scottish wind farms face curtailment of up to 50 per cent of the time, doubling their delivery cost,” Professor Newbery said.

“The European Union is very frustrated with the slow rate at which transmission is being built. There’s now a requirement that each country has to look around and say, ‘in which parts of the country would it be environmentally, sustainably and politically feasible to develop wind farms and solar arrays and then designate these whole regions so that anybody who wants to build in these regions doesn’t need additional consent’.

“They’ve been, as it were, pre-consented, and that seems to be a very sensible approach.

“And something similar would be to say, if all you’re doing is building an additional cable by an existing set of pylons, it should not need the whole tremendously complicated process of citizens’ involvement (…) and all the other things that have to happen before you can do anything anywhere.

“I would argue that it could be done legally quite quickly.”

He added that without reform, consumers would continue to be “shovelling money out to multinational companies”.

Citing the Irish approach to constraint payments, he added: “[Wind farms] can connect in places which have adequate capacity, but if you connect in one of the other places, we won’t guarantee you that you will be paid if you can’t export.

“So when you’re curtailed, that’s your loss, not ours. We don’t have to compensate you.

“In the case of a new wind farm in Shetland, if the existing wind farm has already been guaranteed a firm capacity connection, any new ones would (…) only get paid if they can actually generate.”